Site Temporaries Updates

AES have busy schedule of temporary works ahead of us in the coming year, with several projects up and running or almost ready to go. Below is a list of projects we are involved in during 2020.

Zara Bluewater

We have already commenced on the site temporaries at Bluewater on what will be our third project on this large, Kent based retail centre. We have installed site cabin temporaries and have services on the site area ready and waiting for installation when the steelwork is erected. The project is due for completion in August 2020.

Marriott hotel – City Airport

We are well underway with the site temps on this project and have installed transformers, lighting and local power drops up to level four (there are six levels in total). We have also installed the services to temporary offices that are built and housed on the ground floor. AES are also the main electrical fit out contractor on the 184 room building.

Aldgate East

AES have been assisting with this project which will eventually be a 24 story building. The site is (bordering Aldgate East station) currently undergoing major excavation and archaeological digging (see below).

Excavation works at Aldgate East

AES are providing generators feeding the site cabins, hoarding lights and power for vibration sensors (for the underground). Due to the site constraints regarding the small access area, we have had to be very adaptable and relocate the cabins and generator four times in nine months. AES have also tendered for the main site temps project which would extend our contract until the summer of 2021.

Hayes Machine store

AES are near the end of our contract to supply our site temporaries install for this seven story block of apartments (including underground parking) We have installed a 800 amp supply, a crane supply and power and lighting to all floors, along with power drops. We have also installed water to all floors, power to large hoists, and the site office setup up within the building.

Shurgard Croydon

This new self storage centre is now coming out of the ground and the steel erection is well under way. AES have supplied the generator and will soon be swapping over to the temporary mains. We have also installed water, waste and electrics to the site cabins along with transformers and floodlights. When the site is ready, we we will be installing lights, transformers, power drops and temporary lift supplies.

AES have several other temporary services projects in the tender process and this division of our company continues to grow. For more information about temporary site services by AES please contact a member of our team by clicking here.